Construction Environmental Management Plan (CEMP): Did You Know?
A construction environmental management plan (CEMP) in Queensland is usually required by a condition of a development approval, and the condition states when it is due. Contravening a development approval is an offence under section 164 of the Planning Act 2016, with a maximum penalty of 4,500 penalty units. Much of what a CEMP records is law for the site with or without the condition: the general environmental duty, a 24-hour duty to notify serious or material environmental harm, koala clearing rules, protection of animal breeding places and the general biosecurity obligation.
A construction environmental management plan (CEMP) in Queensland is usually required by a condition of a development approval, and the condition states when the plan is due, commonly before operational works or a pre-start meeting. Contravening a development approval is an offence under section 164 of the Planning Act 2016, with a maximum penalty of 4,500 penalty units. Did you know that most of what a CEMP records is already law for the site, with or without the condition? The eight facts below are the ones we find project teams have not been told.
Do you need a construction environmental management plan?
Work down the table and stop at the first row that describes your project.
| Question | If yes |
|---|---|
| 1. Does a condition of your development approval ask for a CEMP, an environmental management plan or a construction management plan? | You need the plan, by the time the condition states. Read the condition for who has to approve it and what it has to cover. |
| 2. Are you a contractor on a Transport and Main Roads contract that includes MRTS51? | You need an Environmental Management Plan (Construction), and the Administrator assesses it as a hold point. |
| 3. Is there no condition, but the job clears trees, moves soil, or works near a waterway? | No plan is required as a document. The duties in facts 3 to 7 below still apply, and a short plan is a practical way to show how you met them. |
| 4. None of the above? | You are unlikely to need a CEMP. |
The plan is enforceable because the approval is
A development condition is a condition that a development approval is subject to, and section 164 of the Planning Act 2016 says a person must not contravene a development approval, with a maximum penalty of 4,500 penalty units. Once a CEMP is approved under a condition, working outside it can therefore be treated as a breach of the approval. Write only what the site will do, because each commitment in the plan can be checked against what happened.
The CEMP condition comes with the land
Under section 73 of the Planning Act, a development approval attaches to the premises while it is in effect. It binds the owner, the owner’s successors in title and any occupier. A buyer of an approved site inherits the CEMP condition along with the approval, and so does a builder who occupies the site. Ask for the approved plan, and any correspondence about it, as part of due diligence on a site that is sold with an approval.
The general environmental duty applies with or without a plan
Section 319 of the Environmental Protection Act 1994 says a person must not carry out any activity that causes, or is likely to cause, environmental harm unless the person takes all reasonably practicable measures to prevent or minimise the harm. In deciding whether the duty was contravened, the Act allows regard to whether the person used systems to identify, assess and control risks, and whether workers were given information, instruction, supervision and training. Those are the contents of a CEMP: a risk register, controls, inductions and inspections.
Did you know there is a 24-hour clock? A worker who becomes aware of an event that causes or threatens serious or material environmental harm must tell their employer within 24 hours (section 320B). The employer then has 24 hours to give the administering authority written notice (section 320D), with a maximum penalty of 500 penalty units. A CEMP that names who makes that call, and who writes the notice, is how a site meets the deadline on a Saturday.
An incident starts a notification clock
The duty to notify in the call-out above applies to the person doing the work, including a subcontractor’s operator, and it applies from when the person ought reasonably to have become aware of the event. A sediment basin that overtops into a creek, or a fuel spill that reaches a drain, are the kinds of events a construction site should plan for. The incident procedure in the CEMP should give phone numbers, the order of calls and a notice template, so nobody is working out the law while the spill is spreading.
Koala clearing rules apply on top of your approval
In koala district A, which is the South East Queensland region, and in koala district B, a person clearing koala habitat trees must follow the sequential clearing conditions in section 10 of the Nature Conservation (Koala) Conservation Plan 2017. Section 10 says it applies in addition to any other requirement applying to the clearing under an Act, so an approval to clear does not switch it off. The maximum penalty for a contravention is 120 penalty units.
On a clearing site of more than 3 hectares the clearing is staged. For a site of 6 hectares or less, no more than half the site is cleared in one stage, and between stages there must be at least one period from 6pm to 6am with no trees cleared. A tree with a koala in it cannot be cleared, and neither can a tree whose crown overlaps it. Inside a mapped koala habitat area, section 11 also requires a koala spotter to be present when koala habitat trees with a trunk wider than 10 centimetres at 1.3 metres above the ground are cleared. Our koala habitat assessments identify which of these rules apply to a site.
An empty nest can still be protected
Section 335 of the Nature Conservation (Animals) Regulation 2020 makes it an offence, without a reasonable excuse, to remove or tamper with an animal breeding place that a protected animal is using to incubate or rear its offspring. The maximum penalty for that offence is 165 penalty units. A place counts as being used where the animal has used it before to incubate or rear offspring and belongs to a species generally known to return to the same place each breeding season. A hollow or nest with nothing in it on clearing day can therefore still be covered. One of the regulation’s exceptions is removal that is part of a species management program approved by the chief executive, which is why a CEMP for a site with hollows refers to one and schedules a pre-clearing survey.
Driving on and off the site is a biosecurity activity
Section 23 of the Biosecurity Act 2014 gives a general biosecurity obligation to anyone who carries out an activity they know, or ought reasonably to know, is likely to pose a biosecurity risk. The person has to take all reasonable and practical measures to prevent or minimise the risk. Section 23(4) says carrying out an activity includes entering, being present at or leaving a place where biosecurity matter or a carrier is present. Machinery arriving from another job, imported fill and mulch are the usual ways weeds and pests reach a site. In South East Queensland the best known example is fire ants, covered in our fire ant management plan fact sheet.
On Main Roads contracts the plan is a hold point
The Department of Transport and Main Roads specification MRTS51 Environmental Management (March 2025) requires the contractor to develop, implement and maintain an Environmental Management Plan (Construction) for the duration of the contract. Assessment of that plan by the Administrator is Hold Point 1 in the specification, and amendments to the plan are Hold Point 2. MRTS51 also requires the plan to be accessible on site at all times, and requires the contractor’s environmental representative to carry out and document weekly site inspections. Councils and private principals often borrow the same structure for their own contracts.
What a CEMP has to line up with
A CEMP is the document that brings the other approved plans together for the people doing the work, so it is written last and depends on the others being finished.
| Input | Why the CEMP needs it |
|---|---|
| The decision notice and approved plans | Each condition that applies during construction gets a row in a compliance table: what the condition asks, what the site will do, who is responsible and what record proves it. |
| The erosion and sediment control plan | The CEMP refers to it and does not replace it. In Brisbane a medium or high risk site also needs a design certificate lodged at least 10 days before the pre-start meeting, as explained in our post on the Brisbane erosion hazard assessment. |
| Ecology and vegetation reports | Tree protection zones, retained habitat, clearing sequence and fauna spotter requirements come from the ecological assessment and any vegetation management plan. |
| The contractor’s methodology and program | Staging, haul routes, stockpile locations and working hours decide which controls are needed and when. |
The delay we see most often comes from order. A CEMP requested the week before the pre-start meeting cannot be finished if the erosion and sediment control plan or the clearing sequence is still being designed. Commission it when the operational works drawings are issued.
What to do now
Find the CEMP condition in the decision notice. Note when the plan is due, who approves it and every topic the condition lists.
Collect the approved plans, the erosion and sediment control plan, the ecology reports and the contractor’s program before the CEMP is drafted.
Decide who inspects the site each week, who calls the spotter, and who makes the 24-hour notification. Put their names and numbers in the plan.
Queensland Ecologists prepares construction environmental management plans with a condition-by-condition compliance table, and can act as the project’s environmental manager through construction. Call (07) 3018 7538 with the decision notice and the site address.
What a CEMP does not change
Frequently asked questions
Is a CEMP the same as an environmental management plan?
The names are used loosely. A CEMP covers the construction phase. Councils also use environmental management plan, construction management plan and site-based management plan for similar documents, and Transport and Main Roads calls its version an Environmental Management Plan (Construction). The condition or contract says what the document has to contain, whatever it is called. Our environmental management plans page covers the wider group.
Who is responsible for following the CEMP on site?
The approval binds the owner and any occupier of the premises under section 73 of the Planning Act, and the general environmental duty applies to each person carrying out an activity. In practice the principal contractor implements the plan and the developer remains bound by the condition. The plan should say who holds each responsibility.
Which councils are in koala district A and koala district B?
Koala district A is the South East Queensland region under the Planning Regulation 2017. Schedule 1 of the koala conservation plan lists koala district B as the local government areas of Bundaberg, Cherbourg, Fraser Coast and Gympie, with parts of Gladstone, North Burnett, South Burnett and Toowoomba.
How is koala clearing staged on a site larger than 6 hectares?
Section 10 limits each stage to 3 hectares or 3 per cent of the site’s area, whichever is the greater. The 6pm to 6am break between stages applies in the same way, and habitat links have to be kept within the site and to adjacent land while clearing is under way so koalas can move out.
Who can be a koala spotter?
Section 11 defines a koala spotter as a person who has qualifications and experience, or demonstrated skills and knowledge, in locating koalas in koala habitats or in conducting arboreal fauna surveys. The spotter’s primary role during clearing is locating koalas in the trees.
Does a CEMP need updating during the job?
Usually, yes. Staging changes, a new subcontractor or an incident can each make part of the plan wrong. MRTS51 requires a documented process for periodically reviewing the plan, and updates after an incident or a change on site. A council condition may also require an amended plan to be approved again before it is used.