Brisbane Erosion Hazard Assessment: When Small Sites Rate Medium
A Brisbane erosion hazard assessment is lodged with a development application for a material change of use or reconfiguring a lot that will disturb soil. The form asks six yes or no questions, and a yes to any one of them makes the site medium risk or higher. A slope steeper than 5 per cent that runs for more than 3 metres is enough. A medium site needs an erosion and sediment control plan certified by a CPESC or RPEQ, a design certificate lodged with Brisbane City Council at least 10 days ahead, and a pre-start meeting with Council before any soil is disturbed.
A Brisbane erosion hazard assessment is lodged with any development application for a material change of use or reconfiguring a lot that will disturb soil. The form asks six yes or no questions, and a yes to any one of them makes the site medium risk or higher. For a medium site in Brisbane you need an erosion and sediment control plan certified by a CPESC or an RPEQ, a design certificate lodged with Brisbane City Council at least 10 days ahead, and a pre-start meeting with Council’s erosion and sediment control team before any soil is disturbed. Site area is only one of the six questions, which is why a small lot on a slope can rate medium.
This post goes through Council’s form question by question for a small site, then the steps between a medium rating and the first day of earthworks. The statewide picture, including the other South East Queensland councils, is in our post on erosion and sediment control plans in Queensland.
Does the Brisbane erosion hazard assessment apply to your site?
Work down the table and stop at the first row that describes your project.
| Question | If yes |
|---|---|
| 1. Is there no development application at all, and no operational works or compliance assessment application for filling or excavation? | The form is not lodged. The Environmental Protection Act 1994 still applies, so sediment controls go in before the ground is opened. |
| 2. Is there a development application (material change of use or reconfiguring a lot) that will disturb soil, or an operational works or compliance assessment application for filling or excavation? | The Erosion Hazard Assessment form is lodged with the application. Council’s form says that leaving it out may delay the assessment or lead to refusal. |
| 3. Did you answer no to all six questions in Table 1 of the form? | Low risk. Best practice controls are still installed, and no erosion and sediment control plan is lodged with the application. |
| 4. Did you answer yes to any one of them? | Medium or high risk. A certified plan, a design certificate and a pre-start meeting follow if the development is approved. |
The six questions that decide a small site
The current form is CA2085, dated 8 November 2024. Table 1 is the low risk test, and each question is a plain yes or no.
| Table 1 question | What it means on a small site |
|---|---|
| 1.1 Is the area of land disturbance more than 1,000 square metres? | The area counted is soil exposed to rain, including where vegetation, mulch, concrete or bitumen is removed. A full-site strip on a large house lot can pass this mark. |
| 1.2 Does any land disturbance occur in a Council mapped waterway corridor? | One corner of the works inside the mapped corridor is enough for a yes. |
| 1.3 Is there any slope on site, longer than three metres, steeper than 5 per cent before, during or after construction? | A fall of 150 millimetres over three metres is a 5 per cent slope. The question covers the site during and after construction, so a batter formed by the earthworks is counted along with the natural ground. |
| 1.4 Does any land disturbance occur below 5 metres AHD? | Council’s technical notes link low ground to a higher risk of exposing acid sulfate soils. |
| 1.5 Does the development involve endorsement of a staging plan? | A staged subdivision answers yes regardless of its size. |
| 1.6 Is there an upstream catchment of more than 1 hectare passing through the site? | Water arriving from uphill neighbours counts, even where your own site is small. |
Question 1.3 is worth checking first on a small Brisbane site. Five per cent is a gentle slope, the test length is only three metres, and the question asks about the finished landform as well as the ground you start with. A site that answers yes here is medium risk even where it disturbs a few hundred square metres.
Once any answer is yes, Table 2 asks one more question: is the area of land disturbance more than 1 hectare? If it is under a hectare the site is medium risk and the form stops there. A high rating needs more than a hectare of disturbance and a yes to one of three further questions, covering an upstream catchment over 1 hectare, disturbance in a mapped waterway corridor, or a slope steeper than 15 per cent. Most small sites that leave the low category therefore finish as medium.
What a medium rating adds to your timeline
Council’s erosion and sediment control page lists the requirements for a medium site, and each one has to be in place before earthworks start.
| Requirement | Who does it | Timing |
|---|---|---|
| Erosion and sediment control plan | Certified by a Certified Professional in Erosion and Sediment Control (CPESC) or a Registered Professional Engineer of Queensland (RPEQ) with suitable erosion and sediment control qualifications and experience | After approval, before the design certificate |
| ESC design certificate | Signed by the same CPESC or RPEQ | Lodged with Council at least 10 days before the pre-start meeting or the start of site works |
| Pre-start meeting | You request it online. An officer from the Erosion and Sediment Control Team in Compliance and Regulatory Services attends | Before any earth-disturbing activity. Council asks you to allow up to 10 business days for the request |
| Documents on site | The contractor | The certified plan and design certificate are kept on site at all times for inspection |
The delay people meet is in the order of these steps. A design certificate cannot be signed until the plan is drawn, and the plan cannot be drawn properly until the earthworks design is settled. An earthworks contractor booked for the week after approval, with no certifier engaged, is likely to be stood down while those steps are completed. Commissioning the plan when the civil drawings are issued avoids that.
How to book the erosion and sediment control pre-start meeting
The pre-start meeting is requested through Council’s online form, titled Request for an inspection associated with a development approval. On that form you can nominate two preferred meeting times and choose a combined or a separate pre-start meeting service. Council’s guidance says the request asks you to confirm that earlier requirements have been actioned, and that the request should include the certified erosion and sediment control plan and the certified design certificate.
A combined meeting is worth considering where the approval has other conditions that need a pre-start, such as vegetation protection or a construction environmental management plan, because one meeting can then cover the whole set of documents. Have each plan finished and consistent with the others before the request goes in.
What to do now
Run Table 1 against the survey and the earthworks concept before lodging. If the only yes is a batter steeper than 5 per cent, a design change may keep the site low risk.
For a medium site, brief a CPESC or RPEQ when the civil drawings are issued, so the plan and design certificate are ready when the approval arrives.
Lodge the design certificate, request the pre-start meeting online, and hold the earthworks start date until Council has confirmed the meeting.
Queensland Ecologists prepares erosion and sediment control plans certified by a CPESC and RPEQ practitioner, alongside the ecological documents the same approval asks for. Call (07) 3018 7538 with the site address and the approval conditions.
What this does not change
More detail
Who can certify the Erosion Hazard Assessment form?
Council’s supporting technical notes (June 2014) define a suitably qualified or experienced person as someone with professional affiliations with an engineering, environmental engineering, soil science or scientific organisation, or with at least two years of experience in managing soil erosion and sediment control that an independent third party can verify. The certifier signs that the assessment accurately reflects the site’s overall risk, and the form notes that false or misleading information is an offence.
What a high risk site needs
Council’s page says the plan and program for a high risk site are prepared by a CPESC or an RPEQ with suitable qualifications and experience, and the design certificate is certified by a CPESC. An ESC inspection certificate is also completed. It is not lodged, and is kept on site for inspection until all exposed soil is permanently stabilised.
When Council is likely to ask for a sediment basin
The technical notes say a sediment basin will usually be required where the disturbed area exceeds 1 hectare, where the disturbed soils are dispersive, or where run-off turbidity needs to be controlled. They add that soil type or location can lead Council to require a basin on a site under 1 hectare.
Sites below 5 metres AHD
Where the plan is prepared for land below 5 metres AHD, the technical notes require soil pH to be tested under section 7.11.3.3 of the Infrastructure Design Planning Scheme Policy in Brisbane City Plan 2014. They note that a soil pH below 6 or above 8 will usually need treatment before revegetation succeeds.
Upstream catchments
The technical notes require external catchments to be diverted past disturbed soil wherever possible, in a way that does not cause erosion. Where the water cannot be diverted, the upstream area is added to the disturbance area when the drains and sediment controls are sized.
Frequently asked questions
Do I need an erosion hazard assessment for a single house in Brisbane?
The form is lodged with a development application for a material change of use or reconfiguring a lot that disturbs soil, or with an operational works or compliance assessment application for filling or excavation. A house that needs only a building approval commonly has none of those, so no form is lodged. Sediment controls are still required on the site.
Which version of the forms is current?
In November 2026 Council’s website had the Erosion Hazard Assessment form CA2085 dated 8 November 2024, the supporting technical notes dated June 2014, and the design and inspection certificate forms dated March 2015. Download the forms from Council’s page on the day you lodge, as Council replaces them without notice.
Can a design change bring a medium site back to low risk?
Sometimes. The answers depend on the design as well as the land, so keeping disturbance at or under 1,000 square metres, keeping works out of the mapped waterway corridor, or flattening a batter to 5 per cent or less can each change an answer. The natural slope, the site level and the upstream catchment are fixed.
How long before earthworks should the pre-start meeting be requested?
Council asks for the design certificate at least 10 days before the pre-start meeting or the start of site works, and asks you to allow up to 10 business days for a meeting request to be processed. Allow for both when setting the contractor’s start date.
Brisbane site rated medium or high? Queensland Ecologists prepares erosion and sediment control plans certified by a CPESC and RPEQ practitioner for sites across Brisbane and South East Queensland. Request a quote or call (07) 3018 7538.