Queensland Development Application Process: Who Does What
On a vegetated or mapped lot in Queensland, the ecology is best checked at land acquisition, before the contract is unconditional. An ecological constraints analysis reads the State and council mapping and shows the land that is clear. After purchase a town planner leads the development application, and the ecologist supplies the flora survey and the ecological assessment report for council. After approval, conditions commonly ask for vegetation retention, rehabilitation and fauna management plans, and a species management program is needed where clearing will remove an animal breeding place.
On a vegetated or mapped block in Queensland, the ecology is best checked before the contract goes unconditional, because that is the last point at which a finding can change the price or let you walk away. After the purchase, a development application follows a known path: a town planner leads it, a designer and engineers draw it, the council assesses it, and an ecologist supplies the surveys, reports and management plans the environmental provisions ask for. The sections below follow a project from land acquisition through to the conditions of approval and shows where each piece of ecological work is bought.
Queensland Ecologists does the ecology on a development and nothing else, so the planning process is covered here only as far as you need it to see where each consultant fits. Your town planner is the person to ask about the application itself.
Stage 1: land acquisition and ecological due diligence
Most ecological constraints on a lot are published before anyone sets foot on it. An ecological due diligence check reads the State and council mapping over the lot, and where the contract period allows, an ecologist walks the site to see whether the mapping matches the ground. What the buyer gets back is a plan of the lot showing the land that is clear of mapped constraints, the land that is constrained, and the approvals and surveys a development is likely to need.
| What is checked | What it tells a buyer | Who to raise it with |
|---|---|---|
| Regulated vegetation under the Vegetation Management Act 1999 | Where clearing native vegetation can be assessable or prohibited under the Planning Regulation 2017, Schedule 10, Part 3, and whether a subdivision or change of use on a larger lot is referred to the State. | Your planner, and an ecologist where the mapping looks wrong and a PMAV may be worth making. |
| The flora survey trigger map | Whether a protected plants flora survey has to be done before clearing starts. The requirement comes from the Nature Conservation Act 1992 and applies whatever the development approval says. | Run our free protected plant check. |
| Koala mapping in South East Queensland | Inside a koala priority area, development that interferes with koala habitat is prohibited unless an exception such as exempted development applies. Outside a priority area it is assessable. | Your planner, and an ecologist for a koala habitat assessment. |
| Council overlays, waterways, wetlands and matters of State environmental significance | Setbacks and buffers that take land out of the developable area. Depending on the development proposed, a council overlay can also change the category of assessment and add an overlay code, which commonly asks for an ecological assessment report. | Your planner. |
| Matters of national environmental significance under the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) | Which federally listed threatened species and ecological communities, migratory species and wetlands may occur on or near the lot. An action likely to have a significant impact on one needs federal approval, and a council or State approval does not cover it. Deciding whether to refer the action is the proponent’s responsibility. | An ecologist, who checks the federal Protected Matters Search Tool against the habitat on the ground and advises whether an EPBC Act referral is worth considering. |
| Easements, covenants and existing approvals | Legal questions from the title and council searches. Under section 73 of the Planning Act 2016 a development approval attaches to the land, so a buyer takes on its conditions, including a rehabilitation area or a vegetation management plan. | Your conveyancer or solicitor, and your planner. |
The check belongs in the due diligence period for three reasons. Price is the first: the number of lots or the building area the land can yield is what the price ought to be based on, and the mapping can cut it. Timing is the second, since some surveys can only be done in a particular season and a buyer who knows that at the start can plan around it. And a finding made before the contract is unconditional is one your solicitor can still act on, where the same finding after settlement leaves you with far fewer options.
The product we sell for this stage is the ecological constraints analysis, which our due diligence assessments for buyers are built on. Our post on buying land with an environmental overlay goes through the council side in more detail.
Constraints only, or constraints with a site plan
A constraints analysis can be bought in two forms, and which one you want depends on whether a layout exists yet.
State vegetation mapping is drawn largely from imagery. A site walk can find less vegetation than the map shows, or habitat the map has missed. Where the regulated vegetation categories on a lot are wrong, or are right and worth keeping, a property map of assessable vegetation (PMAV) certifies them for that lot under the Vegetation Management Act 1999.
Who does what on a Queensland development application
Section 51 of the Planning Act 2016 asks that an application be made to the assessment manager in the approved form, with the documents the form requires and the fee. The Act is silent on who prepares it, and in practice a town planner leads, because the application is assessed against the planning scheme.
The project team and how the work is handed on
Before the purchase, the ecological due diligence goes to the buyer, the conveyancer and the planner. During design, each consultant’s plans or report goes to the planner, who lodges one application.
What each role does, and what it needs from the others
| Role | What they do on the application | What they need from the others |
|---|---|---|
| Buyer, owner or developer | Buys the land and is the applicant. Sets the brief and the budget, appoints the team, and gives owner’s consent where the Act requires it. | A plain account of what the land can yield, before the contract is unconditional. |
| Town planner | Works out what the development is under the scheme, whether it is accepted, code assessable or impact assessable, and which State referrals apply. Briefs the consultants, writes the planning report, lodges, and manages the statutory periods. | A report from each consultant that answers the code provisions the planner has identified. |
| Designer or architect | Draws the lot layout or the building, and redraws it when a constraint moves. | The constraints map, the survey and the engineering limits, before the layout is fixed. |
| Engineers | Stormwater, earthworks, roads and services, traffic, and geotechnical advice where the site calls for it. | The layout, and the areas of vegetation and waterway buffer that are being kept. |
| Ecologist | Maps the ecological constraints, checks the mapping on the ground, surveys where needed, and writes the ecological assessment against the environmental provisions of the scheme and the State codes. | The draft layout and clearing footprint, and the planner’s list of the codes that apply. |
| Bushfire consultant | Assesses the bushfire hazard and prepares the bushfire management plan where the scheme’s overlay code asks for one. | The layout, and agreement with the ecologist on what is cleared around buildings. |
| Builder, civil contractor, certifier | Build to the approved plans and the conditions. A private certifier can be the assessment manager for the building work. | The decision notice, and each management plan a condition requires before work starts. |
| Council and the State | The council is usually the assessment manager and decides the application. The State Assessment and Referral Agency (SARA) assesses the State matters as a referral agency, or as assessment manager for some applications. | A properly made application. |
Our part as the ecologist is narrow: we report on what is on the ground and how the proposal affects it, against the provisions the planner has identified. Zoning, use definitions and the category of assessment are planning questions, and we send them back to the planner. Where a project has several ecological matters running at once, our DA ecology coordination service manages that work for the planner from the constraints check through to the conditions.
The DA timeline and the ecological work bought at each stage
Nine stages, from buying the land to meeting the conditions
Stages 4 to 6 are the formal process under the Development Assessment Rules. Most of the ecological work is commissioned before and after them.
| What we are asked for | When it is bought | Where the requirement comes from |
|---|---|---|
| Flora survey trigger map check | Stage 1. Free and online. | Nature Conservation (Plants) Regulation 2020. |
| Ecological constraints analysis | Stage 1 as constraints only. Stage 2 with a site plan. | No instrument requires it. It is the buyer’s and the designer’s own check. |
| Federal EPBC Act check, and an EPBC Act referral where one is needed | Stage 1 as part of the constraints analysis. A referral, where one is made, before the action starts. | Environment Protection and Biodiversity Conservation Act 1999 (Commonwealth). |
| Protected plants flora survey | Stage 3, with the other fieldwork, or at stage 8 before clearing starts. | Nature Conservation (Plants) Regulation 2020, section 141, where the clearing is in a high risk area. |
| Ecological assessment report for council | Stage 4, lodged with the application, or at stage 5 in answer to an information request. | The planning scheme’s environmental overlay code. Scenic Rim, for example, has a planning scheme policy for ecological assessments that states the qualifications the author must hold. |
| Vegetation retention plan | Stage 7, before operational works or clearing start. | Usually a condition of the approval. |
| Rehabilitation plan | Stage 7, with monitoring at stage 9. | Usually a condition of the approval. |
| Fauna management plan | Stage 7, before the clearing contractor is on site. | Usually a condition of the approval. |
| Species management program | Stage 8, once the breeding places in the clearing area have been surveyed. | Nature Conservation (Animals) Regulation 2020, section 335. |
Pre-lodgement advice, at stage 3, is optional: councils commonly offer it, some for a fee, and the State Assessment and Referral Agency offers its service free. Use it to ask the council’s environment officer which surveys they expect to see, while there is still time to book them in season.
Running a smaller application yourself
If you are taking a more DIY approach, pay a town planner to review your plans and reports and give you their advice in writing on their own letterhead, then put that advice to council as a pre-lodgement question, paid where council charges for one. It is a fairly cheap and quick way to find out whether the application is likely to meet council’s expectations before you lodge. The planner’s letter and council’s answer also give you a documented path to point to if any part of the application is later challenged.
Once the application is lodged, the periods are those in version 3.0 of the Development Assessment Rules, which commenced on 18 July 2025. Council has 10 business days to make an information request after the application part ends, and you have 3 months to respond.
The 3 month response period is where late ecology costs money. In our experience an ecological information request asks for a report that was missing from the application, for the mapping to be checked on the ground, or for the layout to change. The first two need fieldwork, and some surveys can only be done in a particular season. A layout change means the designer, the engineer and the planner all redo their work inside the same 3 months.
Our post on the common mistakes in responding to an ecological information request covers what to do if you are already at that stage.
The management plans a condition asks for
After the decision, the ecological work is whatever the conditions ask for. Three plans come up most often, and the names vary between councils, so read the condition for what the plan has to contain.
| Plan | What it is for | Who uses it |
|---|---|---|
| Vegetation retention plan | Shows which vegetation stays and which is cleared, and how the retained vegetation is marked and protected while the works go on around it. | The clearing and civil contractors, and the council officer checking the clearing limits. |
| Rehabilitation plan | Describes how an area is to be brought back to native vegetation: the species, the planting, the weed control, and the standard it has to reach before the council accepts it. | The revegetation contractor, and whoever reports the monitoring to the council. |
| Fauna management plan | Describes how animals are managed during clearing: the order the site is cleared in, what happens when an animal or a breeding place is found, and who is responsible for each step. | The clearing contractor and the fauna spotter-catcher. |
The fauna management plan is ours to write, but the fauna spotter-catcher who attends the clearing holds their own permit and is engaged separately, usually by the clearing contractor.
What a development approval does not cover
A development approval authorises development under the Planning Act. Protected plants and animal breeding places are regulated under the Nature Conservation Act 1992, and they have to be checked before clearing even where the council has approved it.
Our post on the flora survey trigger map has the detail. A project likely to have a significant impact on a nationally listed species may also need an EPBC Act referral to the Commonwealth, which is separate again.
Species management programs: low risk and high risk
Section 335 of the Nature Conservation (Animals) Regulation 2020 makes it an offence to remove or tamper with a breeding place that a protected animal is using to incubate or rear its offspring, without a reasonable excuse. A hollow, a nest or a burrow counts. Where clearing will remove one, the tampering can be authorised under a species management program approved by the Department of the Environment, Tourism, Science and Innovation (DETSI). An approved program covers the breeding places only and does not authorise the clearing.
| Program | When it applies | What it involves |
|---|---|---|
| Low risk | The breeding places belong to least concern animals that are not colonial breeders. | Basic information, such as the location of the activity and the area of impact. A register of breeding places is kept and given to the department each year. |
| High risk | The breeding places belong to animals listed as critically endangered, endangered, vulnerable, near threatened or special least concern, or to colonial breeders. | More detailed information for the particular species, with further breeding place survey, impact management, monitoring and reporting. The register is given to the department every six months. |
Which program applies depends on which animals are using the site, so a breeding place survey of the clearing area comes first. The department’s standard processing time is up to 40 business days, and longer if it asks for more information, which is why this survey should not be left to the week the machinery arrives.
What to do first
Have the mapping read, and the site walked if time allows, before the contract is unconditional. Give the result to your conveyancer and your planner.
Ask for the category of assessment and the list of referrals and codes in writing. Every other consultant works from that list.
Add a site plan to the constraints analysis once you have a sketch, and book any seasonal survey then.
The process in more detail
An example: one subdivision, run two ways
The example below is a composite of jobs we have seen, with the details changed. A rural residential lot on the edge of a South East Queensland town is for sale, and the buyer plans to split it into four. Part of the lot is mapped as koala habitat area, and the council’s biodiversity overlay covers the back third.
In the first version the buyer settles on a four-lot price. The designer draws four lots at the minimum size, and the application is lodged with a planning report proposing that the ecological assessment be left to a condition. Council’s information request asks for the assessment up front. On the site walk the mapped habitat proves to be there, with two of the four house sites in it. The layout is redrawn as three lots and the response is lodged close to the end of the 3 months.
In the second version a constraints analysis is done before the contract is unconditional, so the buyer knows the likely yield is three lots and prices the land on that. A site plan is added once the designer has a sketch, and the ecological assessment report is lodged with the application. Either way the land yields three lots, but in this version the buyer pays a three-lot price and for one design.
The five parts of the development assessment process and their periods
From the Development Assessment Rules, version 3.0. A “day” in the rules is a business day, and most periods can be extended by agreement.
| Part | What happens | Period |
|---|---|---|
| 1. Application | The assessment manager decides whether the application is properly made and gives a confirmation notice or an action notice. | 10 business days |
| 2. Referral | The applicant gives a copy of the application to each referral agency. The agency assesses it and responds. | 10 business days to refer. 25 business days for the agency’s assessment unless another period is prescribed. |
| 3. Information request | The assessment manager, and any referral agency, may ask for more information. | 10 business days to make the request. 3 months to respond. |
| 4. Public notification | Applies where any part of the application requires impact assessment, or it includes a variation request. | At least 15 business days for submissions on most applications (Planning Act 2016, section 53). |
| 5. Decision | The assessment manager decides the application and gives a decision notice. | 35 business days to decide, then 5 business days to give the notice. |
The reports the rest of the team prepares
Other consultants prepare these, and we do not offer them. A bushfire management plan and an ecological assessment answer different codes and pull in opposite directions on the same trees, so they are best prepared together.
| Report or plan | Usually prepared by | Where the requirement comes from |
|---|---|---|
| Planning report | Town planner | Addresses the assessment benchmarks: the zone, use, overlay and development codes of the scheme, and any State code. |
| Proposal plans | Designer, architect or surveyor | Required with the approved application form. |
| Bushfire hazard assessment and management plan | Bushfire consultant | The scheme’s bushfire hazard overlay code. Scenic Rim’s code refers to a plan prepared by a suitably qualified person under its planning scheme policy for bushfire management plans. |
| Stormwater management plan, civil engineering | Civil engineer | The scheme’s stormwater and works codes, then the operational works application. |
| Geotechnical report | Geotechnical engineer | The scheme’s landslide or steep land provisions, where they apply. |
| Traffic impact assessment | Traffic engineer | The scheme’s transport code, and the State where a State-controlled road is affected. |
| Landscape plan | Landscape architect or designer | The scheme’s landscaping code or a condition. |
| Arborist report | Arborist | The scheme’s tree protection provisions or a condition, commonly with reference to the Australian Standard for protecting trees on development sites, AS 4970. It assesses individual trees, where an ecological assessment covers vegetation communities, habitat and species. |
Other ecological work a larger project can need
Depending on the mapping and the conditions, a project may also need a koala habitat assessment, a vegetation clearing assessment against State code 16, an MSES assessment, a PMAV, an EPBC Act referral, an erosion and sediment control plan or a construction environmental management plan.
Frequently asked questions
What does an ecological due diligence check cover before buying land in Queensland?
An ecological due diligence check reads the mapping over the lot: regulated vegetation under the Vegetation Management Act 1999, the flora survey trigger map, koala mapping in South East Queensland, matters of State environmental significance, waterways and wetlands, and the council’s environmental overlays. Where time allows an ecologist also walks the site to see whether the mapping matches the ground. The buyer gets a plan of the constrained and unconstrained land and a list of the approvals and surveys a development is likely to need, in time to act on it before the contract is unconditional.
Do I need a site plan with an ecological constraints analysis?
A constraints-only analysis is enough for early due diligence, when no layout exists and the question is whether to buy and what to pay. Add a site plan when you know what you want to build. The proposed house pad, driveway, shed or lot layout is then tested against the constraints and the clearing exemptions before a designer commits to it, and the designer and planner get a buildable envelope.
What is the difference between a low risk and a high risk species management program?
A low risk species management program authorises tampering with the breeding places of least concern animals that are not colonial breeders, and asks for basic information about the activity and the area of impact. A high risk program is for the breeding places of animals listed as critically endangered, endangered, vulnerable, near threatened or special least concern, or of colonial breeders, and asks for species-specific survey, impact management, monitoring and reporting. Both are approved by DETSI under the Nature Conservation Act 1992.
When should an ecologist be engaged for a development application?
An ecologist is best engaged at land acquisition, during the due diligence period, or at the latest before the layout is fixed, on any lot with mapped native vegetation, koala habitat, a council environmental overlay, a waterway or a flora survey trigger map high risk area. At that stage the designer can draw around the constraints. An ecologist first engaged at the information request has 3 months, unless an extension is agreed, to do work that may depend on the season.
Do I need a town planner to lodge a development application in Queensland?
The Planning Act 2016 does not require a development application to be prepared by a town planner. Section 51 requires the approved form, the documents the form asks for, the fee, and the owner’s written consent where the applicant is not the owner and the application is for a material change of use or reconfiguring a lot. Most applicants engage a town planner because the application is assessed against the planning scheme, and the planning report has to address each code that applies.
Does a development approval pass to a buyer when the land is sold?
Under section 73 of the Planning Act 2016 a development approval attaches to the premises and binds the owner, the owner’s successors in title and any occupier. A buyer of land with an approval takes the conditions with it, including any ecological conditions such as a rehabilitation area or a vegetation management plan. Reading the decision notice is part of due diligence.
If you are buying a block or starting a design, send us the lot on plan, any sketch of what you want to build, and your contract or lodgement date, and we will tell you which ecological checks and reports the project is likely to need. Request a quote or call (07) 3018 7538.